Thursday, October 24, 2013

MnDOT Update - Trees starting to be Planted

Eyes on Main Street - October 24, 2013

MnDOT Update - Trees starting to be Planted

Here is the weekly update from MnDOT.

This week in Spring Grove:

  • Grading for sidewalk East of Division Ave.
  • Planting trees West of Division Ave.
  • Installing light poles West of Division Ave.
  • Paving first 2 lifts of bituminous from Division St. to 2nd Ave NE.
  • Pouring light bases East of Division Ave.
  • Paving 2” lift of bituminous from 2nd Ave NE to East project termini.
  • Raising manholes and water shutoffs West of Division Ave.
  • Placing sod West of Division Ave.

 Next week in Spring Grove:

  • Pouring sidewalks and Ped ramps East of Division Ave. 

Highway 44 from Spring Grove to Highway 52:

  • Finished paving 1st lift of bituminous pavement.
  • -Start paving final surface lift of bituminous pavement from Underpass Quarry to Highway 44/Highway 52 intersection.
  • Flaggers and pilot car will now control Highway 44 single lane traffic.



Thursday, October 17, 2013

Council Meeting Update and MnDOT Update

Eyes on Main Street - October 17, 2013

Council Meeting Update


Mayor Poole gave the following update at the October 15th council meeting:


The light poles are starting to be installed; planters are back ordered; sod is hard to find, so peat is being placed instead; the planting beds should be filled with top soil yet this fall; and trees have not arrived yet.


The east side of the project has to pass some more compaction tests before the curb/gutter is installed and asphalt will follow. Also main street will not open until all the curbs and sidewalks are in place. It it too hard to work around parked cars, which means the detour will continue for another 3-6 weeks.


There is some concern with the height of the new street near the hotel. There is about a 4 inch difference to the back alley and about a 9 inch difference at 3rd Avenue SW. Mayor Poole hopes to have more answers after this week's construction meeting. There is also a drainage issue at Marv's. Council person Dehning also mentioned a drainage issue at Grinde's. 

Council stressed again to have all property owners along the construction contact the city with any concerns. They are creating a punch list for items that need to be addressed prior to project completion. Mayor Poole and Council member Nelson both said the October 30 deadline is a rolling deadline. 


Here is an update from MnDOT


This week in Spring Grove:
  • Installing light poles west of Division Ave.
  • Grading Division Ave. intersection for curb and gutter
  • Pouring curb and gutter at Division Ave. intersection
  • Pouring light bases east of Division Ave.
  • Stone wall construction at NW quadrant of 1st Ave. NE
Next Week in Spring Grove:
  • Pouring curb and gutter at Division Ave. intersection
  • Fine grading aggregate base at Division Ave. intersection
  • Planting trees west of Division Ave.
  • Placing topsoil and sod west of Division Ave.
Highway 44 from Spring Grove to Highway 52:
  • Paving 1st lift of bituminous pavement from Underpass quarry to Highway 52 and Highway 44 intersection
  • Flaggers and pilot car will now control Highway 44 single lane traffic

Tuesday, October 15, 2013

Light Poles Starting to be Installed

Eyes on Main Street - October 15, 2013

Light Poles Starting to be Installed

Light poles starting going up yesterday - looking forward to the first time they are "lit". 


Remember you can watch the progress on Spring Grove Communications webcam at http://www.yourlocal.coop/SGC/Main_Street.html.

Also here are some photos SG Communications posted this week on their facebook page (https://www.facebook.com/sgcommunications). 
























Monday, October 14, 2013

MnDOT Update

Eyes on Main Street - October 14, 2013

MnDOT Update

Last week in Spring Grove:

  • Completed backfilling from 1st Ave. NE to Division Ave. intersection
  • Paved from 3rd Ave. NW to Division Ave.  

This week in Spring Grove:

  • Curb and gutter on the east end of the project
  • Prepare for sidewalk to be poured on the east end of the project

 Highway 44 from Spring Grove to Highway 52:

  • Paving first lift of bituminous from Underpass quarry to the west
  • Flaggers and pilot car will now control Highway 44 single lane traffic

Thursday, October 3, 2013

MnDOT Weekly Update

Eyes on Main Street - October 3, 2013

MnDOT Weekly Update

The following just arrived from Kristin Dammueller, Community Relations/Public Affairs Coordinator, MnDOT District 6.

This week in Spring Grove:

  • Sub cut and backfilling from 1st Ave. NE to Division Ave. intersection
  • Sidewalk and Ped ramps West of Division Ave.

 Next Week in Spring Grove:

  • Curb and gutter East of Division Ave.
  •  Placing sand and aggregate base from 2nd Ave. NE to Division Ave. intersection 

 Highway 44 from Spring Grove to Highway 52:

  • Paving first lift of bituminous from Underpass quarry to Spring Grove
  • Flaggers and pilot car will now control Highway 44 single lane traffic


If you have any specific questions regarding work being done in Spring Grove you should contact Tim Hruska at THruska@whks.com.

Please pass along to others who may be interested. This update will also be posted on the project website, www.dot.state.mn.us/d6/projects/hwy44spring-grove/index.html and on the project Facebook page, www.facebook.com/profile.php?id=100003004831362.


Monday, September 30, 2013

MnDOT Update and More Photos

Eyes on Main Street - September 30, 2013

MnDOT Update and More Photos


Here are some photos from this past week. The construction continues with the last phase of the project before the roadway can be finished. It will be a good day in Spring Grove, when the final asphalt is laid. 

Here is the weekly update from MnDOT:

This week in Spring Grove:
  • Pouring Ped Ramps
  • Sanitary sewer/watermain/storm sewer work at Division Ave. intersection
Next week in Spring Grove:
  • Sub cutting and then placing sand and aggregate base from 1st Ave NE to Division Ave. intersection
Highway 44 from Spring Grove to Highway 52
  • Milling bituminous roadway surface from Highway 52 to Spring Grove the week of September, 23rd
  • Paving first lift of bituminous from Underpass Quarry to Spring Grove will begin middle of next week 
  • Flaggers and a pilot car will now control Highway 44 single lane traffic
Here are some photos of the finished limestone wall at school and more. 














And remember to check out the Spring Grove Communications facebook page for more photos https://www.facebook.com/sgcommunications and to check out their web cam. The following pictures are from their site:







Thursday, September 19, 2013

Council Meeting Update and Weekly MnDOT Update

Eyes on Main Street - September 19, 2013


Council Update

Here is an update from the September 17 Council Meeting. All traffic moves to the south detour starting this week. On Friday the plan is to start on the Division Avenue Intersection, which means that intersection will be closed. There has been a delay in the arrival of 3" rock, which has slowed the construction on the east side. Also there has been a delay in sod due to lack of moisture. Even with these delays, the contractor still feels they can finish most items by the October 30 deadline. Also according to Tim Hruska, city engineer from WHKS, Tuesday night at the council meeting, the cost is still under the projected figure due to some of the savings. A few tree species need to be switched to meet the guidelines of the Tree grant. Also the plan is to still apply for the MnDOT Landscape Partnership Grant for the area plantings. 

There was discussion regarding drainage issues. According to the engineer at the council meeting, not all flooding problems are fixed, but hopefully less likely to occur. We still had to deal with the height of current buildings and ADA specifications, however, the engineers designed the best solution possible. There are now four catch basins in front of the Cinema as well as the larger piping for the overflow. There was some concern about the intersection of 2nd Ave NE, but I have not looked at that section. 

Here are some photos from last night. Also the MnDOT update is below the photos and includes the newest detour map.

The rock we still need.


Not so easy to walk to church.


MnDOT Update for this week

This week in Spring Grove:

  • Paving from West termini of project to 3rd Ave SW
  • Move to Phase 3 detour Thursday, September 19th
  • Close Division Ave. intersection
  • Hook up temporary water bypass lines
  • Remove pavement Division Ave. intersection

 Next Week in Spring Grove:

  • Pour curb and gutter East of Division Ave.
  • Finish pouring sidewalk and ped ramps West of Division Ave.
  • Sanitary sewer, watermain and storm sewer work at the Division Ave. intersection 

 Hwy 44 from Spring Grove to Hwy 52:

  • Milling bituminous roadway surface starting Monday, Sept. 23rd
  • Flaggers and a pilot car will now control Highway 44 single lane traffic starting Monday, Sept. 23rd
Phase 3 Detour started today with the closing of Division Intersection.
Phase 3 Detour