Monday, October 14, 2013

MnDOT Update

Eyes on Main Street - October 14, 2013

MnDOT Update

Last week in Spring Grove:

  • Completed backfilling from 1st Ave. NE to Division Ave. intersection
  • Paved from 3rd Ave. NW to Division Ave.  

This week in Spring Grove:

  • Curb and gutter on the east end of the project
  • Prepare for sidewalk to be poured on the east end of the project

 Highway 44 from Spring Grove to Highway 52:

  • Paving first lift of bituminous from Underpass quarry to the west
  • Flaggers and pilot car will now control Highway 44 single lane traffic