Asphalt, Lights, Sod, and Limestone Wall
Progress continues on Main Street. There is a complete layer of asphalt with a final layer yet to be installed for most of Main Street. More lights have been placed and sod is starting to be laid on the West side of town. Curbs are done, now just need the sidewalk poured. The limestone wall near Ola and Per is also complete. Here are some photos from this past week.