Friday, November 15, 2013

Entering the Final Stages and MnDOT Update

Eyes on Main Street - November 15, 2013

Entering the Final Stages and MnDOT Update

The word on Main Street last night was that the final layer was going to begin today. When I left for work this morning, it hadn't started, but they hoped to finish it by tomorrow. Next week will be some final touches as seen in the update from MnDOT below. Watch for details on a grand opening celebration possibly next week!

Here is the update from Jeffrey Bunch - Project Engineer from MnDOT District 6-Winona. 

As a reminder, Highway 44 in downtown Spring Grove is still closed to traffic. There are people sneaking through barricades and driving through downtown.  Please remind your friends and neighbors that they need to continue to use the local detour to get around downtown.

This week in Spring Grove:

  • Finishing up sidewalk and Ped ramps East of Division Ave.
  • Spreading topsoil from Division Ave to the east.
  • Installing light poles from Division Ave. to the east 

Next week in Spring Grove:

  • Installing new street signs.
  • Finishing up installing light poles east of Division Ave.
  • Spreading topsoil and placing sod.
  • Paving final surface lift of bituminous pavement.   

Highway 44 from Spring Grove to Highway 52:

  • Finished paving final surface lift of bituminous pavement from Spring Grove to Highway 52. 
  • Placing aggregate shoulders between Underpass Quarry and Highway 52.  Working from the Quarry to the east next week.
  • Installing edge line rumble strips from the west end of Spring Grove to Highway 52 next week.
  • Placing temporary paint striping along entire project next week.
  • Flaggers and pilot car will continue to control Highway 44 single lane traffic.