Phase 2B Begins Today

Eyes on Main Street - June 10, 2013 


Kristin Kammueller, the MnDOT District 6, Community Relations/Public Affairs Coordinator is sending weekly emails to those involved in the marketing of Spring Grove during the construction. These emails will also be posted on this blog.  On Friday she sent the following recap:
  • Highway 44 is closed with detour for through traffic on Highway 76, Highway 16 and Highway 43 and local traffic is detoured onto 1st Street SW
  • Milled asphalt surface in town from 1st Avenue South SW to Division Avenue
  • Removing concrete pavement under the asphalt
  • Removing contaminated material and hauling offsite
  • Began installing temporary water services to downtown residents/businesses.

 Next Week in Spring Grove:
  •  Hook up temporary water services
  • Begin watermain and sanitary sewer replacement between 1st Avenue SW and Division Avenue

 Highway 44 from Spring Grove to Highway 52:
  • Work scheduled to begin on June 24th
Today she sent the following: "The Phase 2B detour route is going into effect today, June 10. The detour route is attached. The Fire Department has relocated to the City Shop. Because of the move, underground work will begin at  the intersection of Highway 44 and 1st Ave. SW."
Here are some photos from this last week!