Wednesday, August 14, 2013

August 8 Update from MnDOT

Eyes on Main Street - August 9, 2013

Update from MnDOT

This post was never published, so am publishing it today.

The following update came out yesterday from MnDOT.

This week in Spring Grove:

  •  Phase 2A detour in place until further notice
  • Sanitary sewer, water main and storm sewer work between 1st Ave SW and 3rd Ave SW
  • Poured curb and gutter between 1st Ave NW and Division St.
  • Pavement removal between 3rd Ave SW and 3rd Ave NW
  • Sidewalk removal and grading for new sidewalk between 1st Ave NW and Division St.

Next week in Spring Grove:

  • Pour sidewalk from 1st Ave SW to Division St.
  • Remove contaminated material between 3rd Ave SW to 3rd Ave NW
  • Sanitary sewer, water main and storm sewer work between 1st Ave SW and 3rd Ave SW

 Highway 44 from Spring Grove to Highway 52:

  • Bituminous paving at box culvert locations this week
  • Guardrail installation at box culvert locations next week