Update from MnDOT
This post was never published, so am publishing it today.
The following update came out yesterday from MnDOT.
This week in Spring Grove:
- Phase 2A detour in place until further notice
- Sanitary sewer, water main and storm sewer work between 1st Ave SW and 3rd Ave SW
- Poured curb and gutter between 1st Ave NW and Division St.
- Pavement removal between 3rd Ave SW and 3rd Ave NW
- Sidewalk removal and grading for new sidewalk between 1st Ave NW and Division St.
Next week in Spring Grove:
- Pour sidewalk from 1st Ave SW to Division St.
- Remove contaminated material between 3rd Ave SW to 3rd Ave NW
- Sanitary sewer, water main and storm sewer work between 1st Ave SW and 3rd Ave SW
Highway 44 from Spring Grove to Highway 52:
- Bituminous paving at box culvert locations this week
- Guardrail installation at box culvert locations next week