Friday, July 12, 2013

MnDOT Update from July 11

Eyes on Main Street - July 11, 2013

The following update just arrived from Kristin Kammueller, Community Relations/Public Affairs Coordinator, MnDOT District 6.

This week in Spring Grove:

  • Sanitary sewer and water main being installed from 1st Ave NW to Division St.
  • Most lateral services for sanitary and water should be completed by tomorrow.

 Next week in Spring Grove:

  • Continue with sand and Class 6 rock placement between 1st Ave SW and 1st Ave NW.
  • Finish storm sewer and lateral sewer and water services from 1st Ave NW to Division St.

 Highway 44 from Spring Grove to Highway 52:

  • Main detour bypassing Spring Grove via Hwy 43 north of Mabel was reopened Thursday, July 11.  Main detour was closed due to area flooding for two weeks.
  • Box culvert replacements will continue between Mabel and Highway 52.